Figure shows the network for a project. The data for the duration and…
Previous year question for Construction Planning and Management.
Question
Figure shows the network for a project. The data for the duration and costs of each activity are given in the table : Determine the optimum time duration and optimum cost for a project. The indirect cost of the project is 3000.0 per week.
- Year: 2014
- Subject: Construction Planning and Management