Figure shows the network for a project. The data for the duration and…

Previous year question for Construction Planning and Management.

Question

Figure shows the network for a project. The data for the duration and costs of each activity are given in the table : Determine the optimum time duration and optimum cost for a project. The indirect cost of the project is 3000.0 per week.