(a) Explain the following terms : (i) Direct cost (ii) Indirect cost…
Previous year question for Construction Planning and Management.
Question
(a) Explain the following terms :
(i) Direct cost
(ii) Indirect cost
(iii) Cost slope
(iv) Outage loss
(v) Crash time and crash cost.
(b) The network for a job is shown and the requirement of man power per day for various activities in indicated on each activity. Carry out resource leveling for the job. (B-Bar benders and L-labourers) :
- Year: 2014
- Subject: Construction Planning and Management