Construction Planning and Management 2018 Question Paper — Government…
The 2018 Construction Planning and Management previous year question paper (Government College of Engineering and Technology, Jammu), with every question and its marks.
- University: Government College of Engineering and Technology, Jammu
- Subject: Construction Planning and Management
- Course: Construction Planning and Management
- Branch: CIVIL ENGG.
- Year: 2018
- Paper: end-term
- Duration: 180 minutes
- Total marks: 100
Instructions
- Attempt any five questions, selecting at least one question from each module.
- Assume suitable data missing, if required.
Questions
Module 1
- Q1. (a) A target date of completion is to be forecasted based on the following information : 5 Item A — takes 7 weeks for completion Item B — takes 5 weeks for completion Item C — depends on the completion of both A and B and requires 3 weeks for completion Item D — follow up of item C and requires 2 weeks for completion Prepare a Gantt chart for scheduling the completion date. (b) Differentiate between AOA network and AON network. 5 (c) Discuss various network rules. 5 (d) Redraw the network and number it suitably so that each activity can be uniquely defined. 5 [20 marks]
- Q2. (a) For the network shown, if the scheduled completion time of the project is 38 days, determine the critical path and probability of completing the project in 38 days ? Use the following normal distribution table. 10 (b) What is float ? Explain different types of floats. 10 [20 marks]
Module 2
- Q3. (a) The network for a project is shown below. The requirements of mason for each of the activities have been shown in brackets over the arrows in the network diagram. Level out the requirement of the resources if the maximum No. of masons any day has to be limited to 7. 10 (b) Explain the following terms : 10 (i) Cost benefit ratio (ii) Total cost of the project [20 marks]
- Q4. [question text not captured — see original paper]
Module 3
- Q5. [question text not captured — see original paper]
- Q6. [question text not captured — see original paper]
Module 4
- Q7. (a) What do you understand by organization ? Explain various types of organization. 10 (b) Explain the following : 10 (i) Standardization (ii) EOQ [20 marks]
- Q8. (a) What is planning ? Explain the objectives and principles of planning. 10 (b) "Economy Efficiency, Quality and Productivity of a project are dependent on effective inspection". Discuss the statement. 10 [20 marks]