(a). Find out the standard time using the following data Average time…
Previous year question for Production Planning and Control.
Question
(a). Find out the standard time using the following data
Average time for machine element = 12min, Average time for manual elements = 8 min,
Performance rating = 120%, Allowances = 8% [10]
(b). What are the objectives of Work Study? Describe briefly? [10]
- Year: 2018
- Subject: Production Planning and Control