(a) What is dragline ? Explain the factors affecting the output of a…
Previous year question for Construction Planning and Management.
Question
(a) What is dragline ? Explain the factors affecting the output of a shovel.
(b) Estimate the output of a bulldozer for the following operating conditions :
(i) Material = sandy soil
(ii) swell = 25%
(iii) Haul Distance = 45 m
(iv) Mould board size = 3.0 m long and 1.0 m high
(v) Rated mould board capacity = 3 cubic metre loose volume
(vi) Operating factor = 50 min/hr
(vii) Probable round trip time,
Pushing 45 m @ 2.5 kmph = 1.08 min
Returning 45 m @ 5.5 kmph = 0.49 min
Loading, shifting gear = 0.30 min
Total = 1.87 min
- Year: 2014
- Subject: Construction Planning and Management