(a) For the network shown, if the scheduled completion time of the pr…
Previous year question for Construction Planning and Management.
Question
(a) For the network shown, if the scheduled completion time of the project is 38 days, determine the critical path and probability of completing the project in 38 days ? Use the following normal distribution table. 10
(b) What is float ? Explain different types of floats. 10
- Year: 2018
- Subject: Construction Planning and Management