Question
(a) A target date of completion is to be forecasted based on the following information : 5
Item A — takes 7 weeks for completion
Item B — takes 5 weeks for completion
Item C — depends on the completion of both A and B and requires 3 weeks for completion
Item D — follow up of item C and requires 2 weeks for completion
Prepare a Gantt chart for scheduling the completion date.
(b) Differentiate between AOA network and AON network. 5
(c) Discuss various network rules. 5
(d) Redraw the network and number it suitably so that each activity can be uniquely defined. 5